Survey the site properly, design to the smallest measurement with scribed fillers, work from each appliance's installation manual and plan around the services. Check that doors and drawers clear walls and corners, agree delivery access with the building, get the client's signature on plans and finishes, and check every panel against its label on delivery.
A good cabinet design checklist covers the things that cause rework: the site survey, tolerances and scribing, appliances, services, door and drawer clearances, plinths and wall-unit heights, and delivery access. Then get the client's sign-off, check the order before you place it and check the panels when they arrive. The lists below are written to be printed and ticked off on every job, from a single wardrobe to a building of kitchens.
How to use this cabinet design checklist
Work through the groups in order. The survey and tolerances shape the design; appliances, services and clearances test it; sign-off, ordering and delivery protect you once it is agreed. Keep the ticked copy, the signed drawings and the survey photos in the job file. If the site changes after sign-off, such as a new bulkhead or a moved socket, go back to the top.
Site survey
- Every wall measured at three heights (about 100, 900 and 1,800 mm), plaster to plaster. Design to the smallest.
- Both room diagonals taken, and every internal corner checked with 600, 800 and 1,000 mm.
- Ceiling height at each corner, mid-wall and under every bulkhead.
- Highest point of the floor marked, and the fall along each run recorded. Laundry floors usually fall to a drain.
- Walls checked for plumb where tall units and wall units go, with the amount and direction noted.
- Wall construction confirmed: solid block, hollow block or drywall, and stud positions in drywall.
- Windows: position, sill height, reveal depth, opening direction, handle projection.
- Doors: position, opening width, architrave, hinge side and swing.
- AC bulkheads, columns, risers, access panels, fan coil hatches and water heaters located.
- Finishes status recorded. If tiles, skirting, flooring or a false ceiling are still to come, agree and note their finished thickness.
- Every wall photographed with a tape in shot.
Our guide to measuring a room for cabinets sets out the full method if you are briefing a new site measurer.
Tolerances and scribing allowances
- No run designed wall to wall at the full measurement. Leave a filler at each wall end, wide enough to scribe and to let doors and handles clear.
- KutRight fillers are supplied 20 mm wider than the gap, so there is material to scribe to an uneven wall.
- Exposed end panels that meet a wall or floor allowed extra for scribing.
- Out-of-square corners accounted for. A corner 1° out opens about 10 mm over a 600 mm deep worktop.
- Tall units checked for standing up: a 2,100 mm unit 600 mm deep needs about 2,185 mm of ceiling to tip upright; a 2,400 mm unit needs about 2,475 mm.
- Any gap between tall units and the ceiling or bulkhead closed with a scribed panel, agreed with the client.
- Worktop templating and supply agreed: who does it, and when.
Appliances and ventilation gaps
- Model numbers and installation manuals in hand for every appliance before sizes are fixed. The manual decides cut-outs, ventilation and clearances, not the catalogue.
- Fridge: at least 50 mm of air above, plus whatever side and back gaps the maker asks for. A fridge door hard against a wall may not open far enough to pull out its drawers.
- Integrated appliances: ventilation route through plinth or cabinet agreed to the maker's specification.
- Dishwasher: 600 mm wide, or 450 mm slimline, next to the sink, and not hard into a corner where its open door blocks the next run.
- Washer and dryer: typically about 600 × 600 × 850 mm, but check the models. Allow for hoses and plugs behind, and for the dryer's vent or airflow.
- Cooker or hob: 600 or 900 mm, with the side clearance the maker specifies to tall units and walls.
- Extractor hood: 600 or 900 mm, centred and at least as wide as the hob. Most makers ask for at least 650 mm over electric or induction and 750 mm over gas. Much above about 850 mm it won't catch the steam. Duct route or recirculation decided.
More detail in our extractor hood height guide.
Services
- Every socket, switch and isolator drawn on the elevations. Any socket behind a cabinet gets a back-panel cut-out, or the cabinet moves.
- Appliance isolators reachable, not trapped behind an integrated appliance.
- Water supplies and isolation valves reachable inside the sink base.
- Sink waste and washing machine waste: height and position confirmed against the cabinet layout.
- Floor drains kept clear and accessible.
- Holes cut on site for pipes sealed, especially in sink bases and laundries, so damp can't get into the board.
- Gas point and isolation valve accessible. Gas work only by a contractor approved for it.
- AC condensate lines and other concealed pipes located before anyone drills.
- Any electrical or plumbing changes booked with a qualified contractor and finished before the cabinets go in.
Door and drawer clearance
- Internal corners: a filler on each run wide enough for drawer fronts and handles to clear each other.
- Doors hinged next to a wall: filler included so the door opens past 90°. Internal drawers and pull-outs need it.
- Corner fittings (swing-out shelves, magic corner pull-outs, carousels): opening space checked for the chosen fitting.
- Doors checked against window sills, window handles, architraves and the room door's swing.
- Appliance doors checked against neighbouring handles and corners.
- Handle projection allowed for next to walls and tall units.
Plinth and levelling
- 150 mm plinth standard, putting the top of a 720 mm carcass at 870 mm.
- Leg adjustment checked against the floor's fall from the highest point.
- Plinth scribed to the floor, and cut edges sealed in wet areas.
- Removable plinth section under the sink and dishwasher for leak checks.
- Plinth vents fitted where an appliance needs them.
Wall units and fixing heights
- Bottom edge height agreed with the client: 1,350, 1,450 or 1,500 mm above the floor. That is roughly 450 to 600 mm above a 900 mm worktop.
- Whether wall-unit tops line up with tall units decided on the elevations.
- Fixings chosen for the wall: heavy-duty plugs or concrete screws in solid block, fixings made for hollow masonry in hollow block, studs or rated cavity fixings in drywall. Hanging hardware fitted to its maker's instructions.
- Tall units fixed to the wall against tipping.
Labelling and delivery access
- Every KutRight panel carries an ID label that matches the assembly guide. Agree which room each cabinet goes to before the delivery arrives.
- Lift: internal car size and door opening measured against the longest panels. The longest panels, such as tall unit sides, can be up to 2,440 mm.
- Service lift booked if the building requires it.
- Stairs: width, turns and headroom checked.
- Pre-assembled cabinets checked against door widths and corridor turns. Pre-assembled cabinets without glue can come apart to fit; glued ones can't. See delivery and assembly options.
- Building or community rules checked: work permits, delivery times, loading bay, lift protection and working hours.
- Dry, flat, air-conditioned storage on site, away from wet trades.
Client sign-off
- Plan and elevations signed, with dimensions.
- Finishes chosen, ideally from physical finish samples, with grain direction confirmed (vertical by default on doors).
- Handle type and position, and hinge sides, confirmed.
- Appliance models confirmed in writing.
- Inclusions and exclusions listed: worktops, plumbing, electrics, gas, tiling, appliances.
- Delivery date and access arrangements agreed.
A KutRight trade account can produce quotes in your own branding with your margin and labour lines included.
Before you order
- Site re-measured if anything has changed since the survey.
- Every design check in the designer cleared, or knowingly accepted.
- Time allowed for KutRight's free design check, in which a designer reviews every cabinet. It adds one working day.
- Assembly option chosen per cabinet: flat pack, pre-assembled without glue, or pre-assembled and glued.
- Optional hardware kit chosen per cabinet, or your own hardware specified.
- Delivery date matched to the building's booking.
On delivery
- Packs counted against the order summary.
- Panel labels checked against the summary.
- Faces and edges inspected for transport damage before signing. Photograph and report any damage straight away.
- Panels stored flat and dry inside the air-conditioned property.
For trade accounts, project folders and copying a design across units in a building, see KutRight for trade.